igb: increase delay for copper link setup
authorAlexander Duyck <alexander.h.duyck@intel.com>
Tue, 31 Mar 2009 20:38:38 +0000 (20:38 +0000)
committerDavid S. Miller <davem@davemloft.net>
Thu, 2 Apr 2009 07:59:07 +0000 (00:59 -0700)
commita6a605691f666482a261d69da7e0cef7048a434b
tree9bdb28002577e1751b4f5fd45bd8cf766c2a40b3
parentd1a8c9e1c8a49afccc85dfeccd731ccbec52e724
igb: increase delay for copper link setup

Increase the delay for copper phy init from 15ms to 100ms.  This is to
address issues seen in which ethtool -t was failing in some cases on 82576
based adapters.

Signed-off-by: Alexander Duyck <alexander.h.duyck@intel.com>
Signed-off-by: Jeff Kirsher <jeffrey.t.kirsher@intel.com>
Signed-off-by: David S. Miller <davem@davemloft.net>
drivers/net/igb/e1000_phy.c